Item | Cost ($) |
---|---|
Purchased Equipment (PCE) | 8320 |
Purchased Equipment Installation (10%PCE) | 832 |
Instrumentation And Controls (5% PCE) | 416 |
Electrical (10% PCE) | 832 |
Building Including Services (10%PCE) | 832 |
Yard Improvements (2.5% PCE) | 208 |
Service Facilities (10% PCE) | 832 |
Land (2.5%PCE) | 208 |
Total Direct Plant Cost (DPC) | 12,480 |
Engineering and Supervision (5%PCE) | 416 |
Total Direct And Indirect Plant Cost | 12,896 |
Contingency 5% (DPC + IDC) | 644.8 |
Fixed Capital Investment (FCI) | 13,540.8 |
Working Capital Investment (10% FCI) | 1354.08 |
Total Capital Investment (FCI + WCI) | 14,894.88 |